    How to setting AGH-10.2KW-BMS AGH-10.2KW-PLUS? LCD panel setting, battery setting

    Mar 18,2024 | DAXTROMNSOLAR


    Setting Programs:

    Program

    Description

    Selectable option

     

    00

     

    Exit setting mode

    Escape(default)

     

    One-button restore setting options

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

    01

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

     

    Output source priority: To configure load power source priority

    Utility first

     

    Utility will provide power to the

     loads as first priority.

    Solar and battery energy will

    provide power to the loads only

    when utility power is not available.

     

     

     

     

    Solar first(default)

     

     

    Solar energy provides power to

    the loads as first priority.

    If solar energy is not sufficient to

    power all connected loads,utility

    will supply power to the loads at

    the same time.

    Battery provides power to the

    loads only when any one condition

     happens:

    -Solar energy and utility is not

    available.

    -Solar energy is not sufficient and

     utility is not available.

     

     

    SBU priority

     

     

    Solar energy provides power to the

     loads as first priority.

    If solar energy is not sufficient to

    power all connected loads,battery

    energy will supply power to the

    loads at the same time.

    Utility provides power to the loads

    only when battery voltage drops

    to either low-level warning voltage

     or the setting point in program 12.

     

    MKS priority

     

     

    Solar energy provides power

    to the loads as frist priority ,if solar

    energy is not sufficient to power all

    connected loads,utility energy will

    supply power to the loads at the

    same time.

    The battery only supplies energy to

    the load as a backup power.

     

     

     

    02

    Maximum charging current::

    To configure total charging  current for solar and utility

    chargers.

    (Max.charging current =

    utility charging current + solar charging current)

    10A

     

    20A

     

    30A

     

    40A

     


     

     

     

     

     

     

     

    02

     

    50A

     

    60A

     

    70A

     

     

     

    90A

     

    100A(default)

     

    110A

     

     

     

    130A

     

    140A

     

    150A

     

    160A

     

     

     

     

    03

     

     

     

    AC input voltage range

    Appliances(default)

    If selected,acceptable AC input voltage

    range will be within 90-280VAC.

    UPS

     

    If selected,acceptable AC input voltage

    range will be within 170-280VAC.

     

     

     

     

     

     

     

    05

     

     

     

     

     

     

    Battery type

    AGM(default)

     

    Flooded

     

    User-Defined

     

    If "User-Defined"is selected, battery

    charge voltage and low DC cut-off

    voltage can be set up in  program 26,27

     and 29.

    User-Defined

     

    When the solar energy exists,Set this

     item to LIB,and the lithium battery will

     be activated for 3 second.

    User-Defined

     

    If selected,Lithium battery

    communication connection for PACE

     BMS.

     

    06

    Auto restart when overload occurs

    Restart disable (default)

     

    Restart enable

     

    07

    Auto restart when over temperature occurs

    Restart disable(default)

     

    Restart enable

     

    09

    Output frequency

    50Hz(default)

     

     

     

     

     

     

    10

     

     

    Output voltage

    220V

     

    230V(default)

     

    240V

     

     

     

     

     

    11

    Maximum utility charging current

     

    Note:If setting value in

    program 02 is smaller than that in program in 11,the

    inverter will apply charging

     

     

     

     

     

     

     

     

     

     

     

     

    40A

     

     

     

     

     

     

     

    current from program 02 for utility charger

    60A

     

     

    70A

     

    80A(default)

     

     

     

     

    100A

     

    110A

     

     

    |

     

     

    130A

     

    140A

     

     

     

     

     

     

     

     

     

     

     

    12

     

     

     

     

     

     

     

     

    Setting voltage point back

    to utility source when

    selecting “SBU priority”or ‘Solar first”in program 01.

    Available options in 8.2KW/10.2kwmodel:

    42V

     

    43V

     

     

     

     

     

     

    46V(default)

     

     

     

     

     

    49V

     

     

     

     

    50V

     

    51V

     

     

     

     

     

     

     

     

    13

     

     

     

     

     

    Setting voltage point back

    to battery mode when

    selecting “SBU priority”or

    ‘Solar first”in program 01.

    Available options in 8.2KW/10.2kw model:

    Battery fully charged

    48V

     

    49V

     

     

    50V

     

    51V

     

     

    52V

     

    53V   

     

    54V(default)

     


     

     

    55V

     

     

     

    4

     

     

     

    58V

     

     

     

     

     

     

     

     

     

     

     

     

    16

     

     

     

     

     

     

     

    Charger source priority:

    To configure charger

    source priority

    If this inverter/charger is working in Line,Standby or Fault mode, charger source can be programmed as below:

    Solar first

     

    Solar energy will charge battery as first priority.

    Utility will charge battery only

    when solar energy is not available.

    Solar and Utility (default)

     

    Solar energy and utility will charge battery at the same time.

    Only Solar

     

    Solar energy will be the only

    charger source no matter utility is

    available or not

    If this inverter/charger is working in Battery mode or Power saving mode,only solar energy can charge battery.Solar energy will

    charge battery if it's available and sufficient.

     

    18

     

    Alarm control

    Alarm on(default)

     

     

     

     

     

     

     

     

     

     

     

    19

     

     

     

     

     

    Auto return to default

    display screen

    Return to default display screen(default)

     

    If selected,no matter how users

    switch display screen,it will

    automatically return to default

    display screen (Input voltage

    /output voltage)after no button is pressed for 1 minute

    Stay at latest screen

     

    If selected,the display screen will stay at latest screen user finally switches.

     

    20

     

    Backlight control

    Backlight on(default)

     

    Backlight off

     

     


     

    22

    Beeps while primary source is interrupted

    Alarm on(default)

     

    Alarm off

     

     

     

    23

    Overload bypass:

    When enabled,the unit will transfer to line mode if overload occurs in battery mode.

    Bypass disable(default)

     

     

    Bypass enable

     

     

     

    25

     

    Record Fault code

    Record enable(default)

     

    Record disable

     

     

     

     

     

    26

     

     

     

     

    Bulk charging voltage

    (C,V voltage)

    8.2KW/10.2Kw default setting:56.4V

     

    If self-defined is selected in program 5,this program can be set up.Setting range is from 48.0V to 61.0V for 8.2KW/10.2KW model.

    Increment of each click is 0.1V.

     

     

     

     

    27

     

     

     

     

     

    Floating charging voltage

    8.2KW/10.2KWdefault setting:54.0V

     

    If self-defined is selected in program 5,this program can be set up.Setting range is from 48.0V to 61.0V for 8.2KW/10.2KW model.

    Increment of each click is 0.1V.

     

     

     

     

     

    29

     

     

     

     

     

    Low DC cut-off voltage

     

     

    If self-defined is selected in program 5,this program can be set up.Setting range is from 40.0V to 48.0V for 8.2KW/10.2Kwmodel  Increment of each click is 0.1V.Low DC cut-off voltage will

    be fixed to setting value no matter what percentage of load is connected.

     


     

     

    30

     

     

    Battery equalization

    Battery equalization

     

    Battery equalization disable(default)

     

    If "Flooded"or "User-Defined"is selected in program 05,this

    program can be set up.

     

     

     

     

    31

     

     

     

     

    Battery equalization voltage

    8.2KW/10.2kw default setting:58.4V

     

    Setting range is from 48.0V to 61.0V for 8.2KW/10.2kw model.

    Increment of each click is 0.1V.

     

    33

     

    Battery equalized time

    60min(default)

     

    Setting range is from 5min to 900min. Increment of each click is 5min.

     

    A

    I

     

    Battery equalized timeout

    120min(default)

     

    Setting range is from 5min to 900 min. Increment of each click is 5 min.

     

    35

     

    Equalization interval

    30days  (default)

     

    Setting range is from 0 to 90 days. Increment of each click is 1 day

     

     

     

     

     

    36

     

     

     

     

    Equalization activated

    immediately

    Enable

     

    Disable(default)

     

    If equalization function is enabled in program 30,this program can be set up. If "Enable"is selected in this program,it's to activate battery equalization immediately and LCD main page will shows  .If "Disable"is selected,it will cancel equalization function until next activated equalization time arrives based on program 35

    setting.At this time   will not be shown in LCD main page.

     

     

     

     

    37

     

     

     

     

    GRID-tie operation

    Off grid (default)

     

    Inverter operates only in off-grid

    mode.Solar energy provides power to

    the loads as first priority and charging second

    Hybrid

     

    Inverter operates hybrid mode.Solar

    energy provides power to the loads as first priority and charging second

    Excess energy feed to grid.

     


     

    38

     

    GRID-tie current

    10A

     

     

    Increment of each click is 2A.

     

    39

     

    Led pattern light

    Led pattern off

     

    Led pattern on(default)

     

     

    41

     

    Dual output

    disable(default)

     

    use

     

     

     

     

     

    42

     

     

     

    Enter the dual output

    functional voltage point

    8.2KW/10.2kw default setting:44.0V

     

    Setting range is from 40.0V to 52.0V for 48VDC model.

    Increment of each click is 0.1V.

     
     

     